Housing & Food Services
Snyder/Phillips MSU Bakery University Village
  Mayo Hall
Contact Us
Home

Mayo HallMayo Hall, in West Circle Complex, built in 1931, is the oldest Residence Hall on campus. Mayo Hall has been closed for the year from May 2008 to August 2009 for an upgrade of all major mechanical, electrical and ventilation systems, elevator installation, asbestos abatement. The hall will also undergo lighting upgrades, flooring and ceiling replacements, roofing and exterior repair, office modifications, reconfiguration of the community bathrooms, replacement of existing plumbing and furnishings and other related improvements. An upgrade will also be made to all of Mayo’s life safety systems, including sprinklers, smoke detectors and fire alarm systems.

Watch in the coming year as we renovate Mayo Hall into a more modern look, keeping the feel of the quaint style of the past.

 


 
July 23

Mayo Hall

All windows on the exterior of the building, facing Michigan Avenue have been removed and replaced with a temporary covering until new windows are installed. The concrete in the courtyard area facing Michigan Avenue has been removed and workers are leveling the ground and piles of dirt and pea gravel are all around. Inside, the floor, ceiling and walls have been stripped bare throughout the main floor common areas. Outdoor utility work continues in the West Circle parking lot area.

 


  July 15

Mayo Hall

Mayo’s basement has a near-completed cement floor and work continues on the main floor and in the front lobby. On the exterior of the building, crews are working to replace the empty window frames with new windows with modern locks and closures.

Mayo Hall

 


 
July 3

Mayo Hall

Mayo HallDemolition is progressing on the interior of Mayo, including work in the basement, main floor and second and third stories. Walls and doorways continue to be removed, most notably in the community shower rooms and restrooms. On the exterior of the building, various windows have been removed on the Michigan Avenue side of the hall and boarded up with either plastic or wood. Crews outside continue to dig and install underground utility piping before students arrive this fall.

 


 
June 27

Mayo Hall

An increasing number of community bathrooms and shower rooms on all floors are being gutted. For example, all that is left of what was the second floor bathroom is the Spartan wall trim; everything else has been removed and there are large holes in the floor for workers to utilize for debris removal and continued construction. Debris from Mayo’s demolition is being removed from the third floor center window facing Michigan Avenue. The floor in Mayo’s basement has been removed, revealing the earth below.

Mayo Hall

 


 
June 19

Mayo Hall

Heavy demolition continues in the various basement rooms and areas and the incinerator continues to be disassembled. Community bathroom shower and toilet stalls are indistinguishable and ceiling tiles and fixtures have been removed. Light fixtures and smoke detectors continue to be removed and several walls and doorframes have been demolished on the second floor student wing, among others.

Mayo Hall

 


 
June 11
Mayo Hall

Flooring has been torn up in Mayo’s student rooms. Select doors have been removed and crews have marked several walls and door frames for demolition. Some bathrooms and shower rooms have been stripped and some still house marble and plaster rubble. The light fixtures have been torn out as well as outlets and electrical systems. Work also aggressively continues on the outdoor utility project. Many materials have been recycled and reused during the demolition, including concrete, masonry, marble, steel, wood among others.

Mayo Hall
 


 
June 3

Mayo Hall

Mayo HallWork crews inside are demolishing all community bathrooms and shower rooms, removing marble services and taking out plaster. Workers continue to take apart the original brick incinerator, running from the basement to the roof, to make way for the new elevator. Crews are also pulling out all light sockets and electrical outlets and taking out select main hallway and stairwell doors.

 


 
May 30

Mayo Hall

Both the massive outdoor Physical Plant-funded utility project and numerous indoor renovations are in full swing at Mayo. Outside, crews working on “The Big Dig” have installed sheet metal shoring to hold back the earth and prevent it from caving in on workers as they lay new utility groundwork. Mayo’s outdoor utility project will be completed before the close of summer and work crews are working sun-up to sun-down, six days a week.

Inside, contractors are working on everything from asbestos abatement, to demolition of all community bathrooms (including shower rooms and restrooms) and the original brick incinerator. A new elevator will be installed where the incinerator once stood.

 


 
May 22
Mayo Hall

Demolition is in process inside of Mayo and outdoor utility work continues.
 


 
May 15

Mayo Hall

Demolition is still in the early phases at Mayo. Work is being done outside of the hall and work crews are starting to lay new utility pipes.

 


 
May 7

Mayo Hall

Demolition has begun as they tear out existing carpet, wall coverings, cabinets and other equipment to make way for the improvements.

Mayo Hall

 


Michigan State University